2017
04/12/2017

OME aquires Wabuska geothermal assets

OME aquires Wabuska geothermal assets

Salt Lake City, Utah April 12, 2017 – Open Mountain Energy, LLC (“OME”) acquired geothermal related assets of the Wabuska Geothermal Project from Homestretch Geothermal 2010, LLC (“Homestretch”).  Wabuska is the oldest operating geothermal plant in Nevada, beginning operation in the 1980’s.

08/10/2017

OME breaks ground at Wabuska site

OME breaks ground at Wabuska site

Ground breaking begins:  OME commences development by replacing the existing power generation with Kaishan power generation equipment. OME expects the first phase of development to be online by the end of 2017 with a beginning generation of 4 MW of net power.

08/14/2017

OME Geothermal Equipment Arrives

OME Geothermal Equipment Arrives

Kaishan Group’s geothermal power generation equipment arrives at the White Grass build site – factory assembled and pre-tested.

10/21/2017

Geothermal Power Equipment Set

Geothermal Power Equipment Set

Due to Kaishan’s pre-assembled and factory tested modular power equipment, plant installation is nearly complete months ahead of industry standards.

2018
01/18/2018

OME’s Initial Synchronization to the Grid

OME’s Initial Synchronization to the Grid

OME’s new Wabuska geothermal power plant comes online in January, just 6 months after breaking ground.  This is perhaps the shortest duration of any geothermal plant construction ever.

02/22/2018

Commissioning of All Four Power Units

Commissioning of All Four Power Units

OME brings all four geothermal power units up to full operation, running concurrently, and synced to the grid.

03/03/2018

Star Peak Geothermal Project Site – Flow Test

Star Peak Geothermal Project Site – Flow Test

OME successfully flow tested two main production wells.  Star Peak power plant scheduled for completion in Q1 – 2019, starting with 12 MW.